Zero Two Enters Into JV to Develop First Middle East Mining Op
Zero Two, a digital assets development company based in Abu Dhabi in the United Arab Emirates (UAE), has partnered with leading North American crypto miner Marathon Digital in a joint venture that will result in the development and operation of the Middle East’s first large-scale crypto mining facility.

Initial capacity of 250 MW
In a press release issued on Tuesday, Marathon Digital outlined that the venture is focused on accelerating the global digital economy while also supporting Abu Dhabi’s power grid.
To progress the project, the two companies have formed the Abu Dhabi Global Markets JV Entity (AGDM Entity). Initially, two digital asset mining facilities, with a combined capacity of 250 MW, will be developed.
One site, at Masdar City, Abu Dhabi, will account for 200 MW of that capacity. The remaining 50 MW capacity will be developed at a site located in the port area of Mina Zayed. The strategy of the firms is to exploit excess network energy in Abu Dhabi. The firms see this as a win/win as increasing the base load of the Abu Dhabi power grid will result in a more sustainable grid. The companies intend to supplement any use of non-sustainably produced energy with carbon offset certificates.
80/20 equity split
The two firms have agreed upon an 80%/20% equity split, with Zero Two being the lead investor. In the initial development period for the venture during 2023, both entities will contribute resources to the joint venture in proportion to the equity division, in the form of capital, equipment and infrastructure.
Zero Two and Marathon had previously collaborated on a pilot project with the objective of determining the feasibility of building a large-scale facility. Air-cooled miners have not proven to be a success in hot arid climates like that of the Rub Al Khali Middle Eastern desert.
The upshot of the pilot program was a determination that a custom-built immersion-cooled system would be feasible. Mining equipment for the facilities is already on order while construction at the two sites is underway. Both sites are expected to go online before the end of the year with a combined hashrate of 7 EH/s.
Ahmed Al Hameli commented on the joint venture: “This alliance leverages Zero Two’s regional expertise, expansive relationships, and growing blockchain infrastructure development and operational capabilities, with Marathon’s technical prowess in developing digital asset sites and innovative mining technologies.
These synergies create a powerful combination and lay the groundwork for the success of this pioneering project in the Middle East. Marathon shares our commitment to actively supporting Abu Dhabi’s power grid and developing global digital assets infrastructure. We look forward to working with them on this venture.”
Jurisdictional arbitrage
Marathon’s CEO Fred Thiel said that Zero Two’s regional relationships were an optimal compliment. It may be both a timely and shrewd move by Marathon to develop this project in the Middle East region. In recent weeks the Biden administration floated the idea of a 30% crypto mining tax. Crypto mining is a global endeavor.
That type of additional overhead would make it very difficult for North American miners to remain viable. By opening up new working relationships in other regions, the company may be in a better position to pivot should North America and the firm’s Montana-based mining facility become unsustainable.